Exhibitor Field Guide First-show checklist, in order

First-show checklist, in order

Exhibiting is a deadline problem wearing a marketing costume. This page is the timeline, in the order the deadlines actually arrive.

Dates below are relative to show open, and every one of them yields to the dates printed in your show's own documents. The single most useful thing you can do with this page is transcribe it into a dated list the day you sign, then update it the day the services manual appears.

At contract signing

Three to four months out

When the services manual publishes

Usually sixty to ninety days out, and this is the busiest hour of the whole project.

Two to three weeks out

What to pack

A show kit, in a case you carry rather than ship: box cutter, gaffer tape, zip ties, scissors, multi-tool where badge rules allow, extension strip for back-of-booth charging, spare phone chargers, cleaning wipes, trash bags, first-aid basics, printed copies of every order confirmation and the freight paperwork, spare "EMPTY" labels, and a marker. Someone will need every item on this list, usually within the first hour of move-in.

Move-in day

Show days and teardown

Each morning: fifteen minutes early, stock check, lead device charged. Each evening: sync and back up lead data — never let it live only on one device overnight.

At close: nothing comes down before the official closing minute; show managers notice. Photograph the booth before packing, photograph packed crates and their labels, and keep the material handling agreement and carrier paperwork copies. Empties return slowly — plan for hours, not minutes. Before leaving the hall, photograph your empty space. Those photographs are your evidence for damage claims, missing-freight claims, and rental disputes, and they cost nothing to take.